AES EN PANAMÁ S . DE R . L .
LATIN AMERICA which – after being optimized by AES – deliver 47.2MW , 54.8MW and 260MW , respectively . New plants AES built in Panama during recent years contribute additional power :
• Changuinola I , built in the Palo Seco Forest Reserve , Bocas del Toro province , supplies 223MW .
• Estí , in the Chiriquí province , has the capacity to supply 120MW to the National Interconnected System ( SIN ).
• Estrella del Mar I hopper barge , was delivered during the 2013-2014 drought caused by the El Niño phenomenon . The barge supplies 72MW to SIN .
• The AES Colón , located in the province with this same name , comprises construction of a LNG plant , a tanker and a dock . This US $ 1 billion investment will be able to supply 350MW starting in 2018 . The project ’ s estimated completion time is 30 months , involving POSCO E & C ’ s resources and GE power generation equipment . The Colón project employs 2,000 workers for its construction .
Standard compliance extends beyond AES and onto suppliers and partners
www . aespanama . com 61